Construction - Western Rural Water, AZ Fort Tuthill County Park Quad Water-Sewer Replacement

U.S. Army Corps of Engineers, Los Angeles District
Published April 17, 2023

595 AUTHORITY & PURPOSE:
Water Resources Development Act (WRDA) 1999 Section 595 authorized the U.S. Army Corps of Engineers (USACE) to provide design and construction assistance for water supply, wastewater treatment, environmental restoration, and surface water protection to  rural communities. Section 4008 of the Water Resources Reform and Development Act of 2022 amended WRDA 1999 Section 595, authorizing $490M for technical assistance to small and rural communities in Idaho, Montana, Nevada, New Mexico, Utah, and Wyoming. WRDA 2020 added a $150M authorization for Arizona projects with WRDA 2022 increasing the authorization by $50M ($200M total). Projects are to be cost shared 75% Federal and 25% non-Federal. The Federal share may be in the form of reimbursements.

ACTIVITIES FOR FY 2023: Activities include initial project coordination and development of a project scope working toward execution of a design and construction project partnership agreement (PPA) with Coconino County for the Fort Tuthill County Park Quad Water-Sewer Replacement. New Start FY23.

FY 2024 PLANNED ACCOMPLISHMENTS: Planned carryover funds will be used to coordinate the project scope, negotiate, execute the PPA, complete design and initiate construction.

ISSUES AND OTHER INFORMATION: Fort Tuthill County Park is a critical regional recreational asset. Recently, the County invested nearly $2M in the installation and connection of new sewer lines between the park and the City of Flagstaff. Replacing aged water and sewer lines would further tie-in the park to the City of Flagstaff’s wastewater system and address water quality concerns regarding lead joints and septic overflows. Work under the 595 Program will include efforts to tie Fort Tuthill facility into the newly installed sewer and water lines.

AUTHORIZATION: WRDA 1999 (P.L. 106-53), Sec. 595; WRDA 2007 (P.L. 110-114), Sec. 5067; Energy and Water Development Appropriations Act (EWDAA) 2004 (P.L. 108-137), Sec. 117; EWDAA 2010 (P.L. 111-85), Sec. 112(2); Water Infrastructure Improvements for the Nation Act 2016 (P.L. 114-322), Sec. 1186; WRDA 2020 (P.L. 116-260), Div. AA, Sec. 352

As of: 01 Mar 23
FINANCIAL SUMMARY:       CONSTRUCTION
Estimated Federal Cost            $3,300,000
Estimated Non-Federal Cost            $1,100,000
Total Estimated Project Cost            $4,000,000

Allocation thru FY22                           $0
President’s Budget for FY 23                           $0

Conference Add for FY23          $3,300,000 
Approved IIJA FY 23                          $0
Workplan for FY 23                          $0
President’s Budget for FY24                          $0
Workplan for FY24                       TBD
Balance to Complete After FY24                          $0
 

 

CONGRESSIONAL INTEREST: Senators Kelly and Sinema; Representatives Crane (AZ-02), Stanton (AZ-04)

 

U.S. ARMY CORPS OF ENGINEERS – LOS ANGELES DISTRICT
915 WILSHIRE BLVD., SUITE 1109, LOS ANGELES, CA 90017
http://www.spl.usace.army.mil


Contact
Congressional Liaison
executiveoffice.spl@usace.army.mil