A public notice is the primary method for advising all interested parties of a proposed activity for which a permit is sought. Soliciting comments and information necessary to evaluate the probable impacts on the public interest. Public notices are also published to inform the public about new or proposed regulations, policies, guidance or permit procedures.  

Public Notices published by the Los Angeles District are posted on these three pages. There are two types of Public Notices; Regulatory and Project Public Notices. Comments are due by the expiration date of the public notice. 

Only comments submitted by email or in hard copy format through a delivery service, such as the U.S. Postal Service, can be accepted.   Comments must be submitted to the address listed in the public notice.

Public Notice Manager

SPL-2020-01-RL-KW Riverside Levees Repair

ERB
Published Feb. 10, 2020

Riverside Levees Repair Project

The U.S. Army Corps of Engineers (Corps) proposes to repair damages to the Riverside Levees.  The levees are on the Santa Ana River in Riverside County, California within the vicinity of State Route 60 (Pomona Freeway), Mission Avenue and Market Street. See project map below.

High flows from past storms through this reach as well as migration and impingement of the low-flow channel against the levees resulted in damages requiring repair. Preliminary damage assessments and conceptual repair designs have been completed. Engineering and environmental planning efforts to implement repairs are now underway.   

The overall goals of the repair project are to (1) improve resistance to scour and erosion to better maintain the existing level flood risk minimization, and (2) reduce future in-channel maintenance requirements.

The reach of river where damages occurred is designated as critical habitat for the Santa Ana sucker (Catostomus santaanae), a fish species protected under the Endangered Species Act (ESA).  The Corps and the U.S. Fish and Wildlife Service (Service) are coordinating closely to minimize impacts to the fish and its habitat during construction and subsequent in-channel maintenance activities.  Repair designs that would reduce future in-channel maintenance requirements are under investigation.  Reduction of future in-channel maintenance requirements would benefit both the fish and its habitat.  Formal consultation with the Service under the ESA will occur as alternatives are further developed and the preferred alternative is identified.

Preliminary environmental analysis indicates that potential impacts to environmental resources including the Santa Ana sucker are likely to be less than significant or can be mitigated to a level that is less than significant pursuant to the National Environmental Policy Act (NEPA).  Pursuant to NEPA, the Corps is preparing an Environmental Assessment (EA) to evaluate potential environmental impacts of the proposed repairs and future operations and maintenance activities that may be required. If the EA identifies significant impacts that cannot be mitigated to a level that is less than significant, an Environmental Impact Statement would be prepared.

Comments will be accepted from February 10, 2020 to March 10, 2020. Comments can be submitted electronically to: kenneth.wong@usace.army.mil

Alternatively, comments can be mailed to:

U.S. Army Corps of Engineers

Kenneth Wong, Planning Division

915 Wilshire Blvd., Los Angeles, CA 90017